Velocity — work completed per sprint.
Calculation: Velocity = Total story points completed
Use cases:
Example:
Sprint History:
Sprint 1: 25 points
Sprint 2: 28 points
Sprint 3: 22 points
Sprint 4: 30 points
Average: 26.25 points
Release forecast:
Backlog: 105 points
Velocity: 26 points/sprint
Estimate: 4-5 sprints
BA role: